Here is an example ... I get a call to do a quote ... a regular customer.
It takes me 5 days to compile the quote ... back and forth to site measuring ... opening panels ... identifying cable routes and how to secure the tray and because it is on comunal property ... we have to get permission to work in front of other companie's entrances ... etc etc.
Design ... which includes cable sizing ... panel upgrade ... cable trays ... underground sleeves.
Create a bill of qualities ... a full material list and I send it for pricing.
Friday afternoon I send the quote to the customer R876 000.00 (rounded off)
The customer calls me a week later to inform me that they only plan to do the project in 5 years time ... so I send them a bill for R6000 for my time ... thats were the fight started.
I doubt an electrical consulting company would only charge R6k for all that work ... but maybe I live in coco land where people dream of making R6k for creating a document ready for a tender.
It takes me 5 days to compile the quote ... back and forth to site measuring ... opening panels ... identifying cable routes and how to secure the tray and because it is on comunal property ... we have to get permission to work in front of other companie's entrances ... etc etc.
Design ... which includes cable sizing ... panel upgrade ... cable trays ... underground sleeves.
Create a bill of qualities ... a full material list and I send it for pricing.
Friday afternoon I send the quote to the customer R876 000.00 (rounded off)
The customer calls me a week later to inform me that they only plan to do the project in 5 years time ... so I send them a bill for R6000 for my time ... thats were the fight started.
I doubt an electrical consulting company would only charge R6k for all that work ... but maybe I live in coco land where people dream of making R6k for creating a document ready for a tender.