Simple answer ....... No. Sections 2 and 4 do not need to be completed.
Describe in section 3 the part of the installation covered by your COC.
You will be issuing a supplementary COC and you have to refer to the existing COC, quoting it's number and date of issue.
If there is no existing valid COC for the installation, then it is not possible to issue a supplementary COC.
Cheers and peace out
Derek